天池抽水蓄能电站上坝址趾板建基面优化研究
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
通过现场调查结合勘测资料分析了天池抽水蓄能电站上坝址蚀变岩体的分布规律;利用薄片鉴定、电镜扫描及X射线粉晶衍射分析试验对蚀变岩体进行了岩石成分和化学成分分析,研究了蚀变作用的地质成因、蚀变机理,结合室内试验获得了蚀变岩的物理力学指标;利用FLAC3D软件对不同工况、不同高程河床蚀变岩趾板建基面进行了数值分析计算。研究结果表明:在左岸和右岸由于强风化下限埋深不大,建议挖除,趾板建基面选择在中等风化的中条期混合花岗岩上;控制坝基变形的主要地质因素是存在于坝基范围内的断层破碎带F_(25)断层以及断层周围由于蚀变造成的砂状岩芯,对大坝沉降影响不利;河床蚀变岩趾板建基面优化数值模拟研究表明,河床部位以在930~950 m之间作为趾板建基面是适宜的。
By combination of survey data and field investigation of the Tianchi pumped storage power station dam,the distribution of altered rock was researched.By use of thin section identification,scanning electron microscope and X-ray diffraction analysis test,the altered rock of rock composition and chemical composition was analyzed.The geological causes of alteration and alteration mechanism was studied and the physical and mechanical parameters of altered rocks were obtained with laboratory experiments;altered rock riverbed toe slab foundation is numerically calculated and analyzed by using FLAC3 D software in the different conditions and the different elevations.The results show that:on the left bank and right bank of the maximum depth of weathering is not as strong and the proposed excavation and toe slab foundation was in the bar in the middle of the mixed granite;the alteration of sand-like core presented in the range of dam foundation F_(25) fault and around the fault zone is the main geologic factors of dam deformation and the adverse impact of the dam settlement;the numerical simulation of river altered rock toe slab foundation optimization showed that the riverbed of the 930 ~ 950 m elevation being as base surface is appropriate.
引文
[1]李文诚.抽水蓄能电站工程地质问题分析研究[M].北京:地震出版社,2001.
    [2]张辅纲,涂希贤.粘土化蚀变花岗岩的工程地质特性[J].广东地质,1994(3):48—50.
    [3]DeLucia E H,Schlesinger W H,Billings W D.Water relations and the maintenance of sierran conifers on hydrothermally altered rock[J].Ecological Society of America,1988,69(2):303-311.
    [4]Crowley J K,Zimbelman D R.Mapping hydrothermally altered rocks on Mount Rainier[J].Geology,1997,25(6):559-562.
    [5]Wang A,Korotev R L,Jolliff B L,et al.Evidence of phyllosilicates in Wooly Patch,an altered rock encountered at West Spur,Columbia Hills,by the Spirit rover in Gusev crater,Mars[J].Journal of geophysical research,2006,111(E02S16):1-22.
    [6]廖建强.广州抽水蓄能电站地下洞室区蚀变岩的工程处理[J].岩土工程界,2002,5(9):48-50.
    [7]张永双,曲永新,刘景儒,等.滇藏铁路滇西北段蒙脱石化蚀变岩的工程地质研究[J].岩土工程学报,2007,29(4):531-536.
    [8]杨燕,付小敏.某工程蚀变岩抗剪强度特性的影响因素[J].实验室研究与探索,2009,28(1):42—45.
    [9]于新华,翦波.蚀变花岗岩工程特性研究[J].西部探矿工程,2007(6):94—96.
    [10]王仁坤,林鹏.溪洛渡特高拱坝建基面嵌深优化的分析与评价[J].岩石力学与工程学报,2008,27(10):2010-2018.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心