唐山市玉田县大和平闸地基不均匀沉降原因分析
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
大和平节制闸自竣工并投入运行已有36年。2009年1月安全检测结果显示,闸室左侧基础沉陷,控制室部位的交通桥桥面比中部桥面低40cm,左侧护坡比闸墩多沉陷5cm,闸基在垂直水流断面上呈现出明显不均匀沉降。在地质勘察工作基础上,对大和平闸地基不均匀沉降原因和机理进行分析、研究,为除险加固设计提供依据,并提出处理措施及建议。
Since the completion of the Daheping sluice and put into operation for 36 years. In January 2009, safety inspection according to the results, lock chamber on the left side of the foundation settlement, control room of 40 cm lower than the central bridge traffic bridges, on the left side of the slope protection than the pier subsidence 5 cm, brake based on the vertical flow section presents obvious uneven settlement. On the basis of geological prospecting work, brake to great peace and the reason of foundation uneven settlement mechanism analysis and research, provide geological basis for design and consolidate, provide geological basis for design and consolidate, and guiding treatment measures and suggestions are put forward.
引文
[1]河北省水利水电勘测设计研究院.玉田县大和平节制闸除险加固工程初步设计工程地质勘察报告[R].2009.
    [2]GB50007—2011,建筑地基基础设计规范[S].
    [3]GB50487—2008,水利水电工程地质勘察规范[S].
    [4]GB18306—2001,中国地震动参数区划图[S].
    [5]JGJ79—2012,建筑地基处理技术规范(第二版)[S].
    [6]地基处理手册编委会.地基处理手册(第二版)[K].北京:中国建筑工业出版社,2006.