强震区软基上泵站地下连续墙注浆加固方案研究
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
为解决高地震烈度区睢宁泵站软弱地基问题,提出了一种新型板肋式地下连续墙与土体注浆加固的设计方案。结合泵站结构的布置特点,建立了三维非线性有限元计算模型,分别从肋宽、注浆深度和土体强度参数的提高幅度这3个方面,对板肋式地下连续墙的水平位移进行了静、动力有限元分析。结果表明,板肋式挡墙结构在墙背土体注浆深度为19.5 m、土体变形模量提高10倍以上、粘聚力提高1.5~2倍和内摩擦角增加2°~4°时,墙体的水平位移便能得到有效的控制。通过实例研究,验证了该加固方案的合理性和有效性。
In order to solve the problem of soft foundation of Suining Pumping Station in the area with high earthquake intensity,this paper presents a new design scheme for sheet-rib underground continuous retaining wall and reinforcement grouting.According to the arrangement features of the structure of pumping station,a 3D nonlinear finite element model was set up and the static and dynamic finite element analysis were carried out on the horizontal displacement of sheet-rib underground continuous retaining wall from three different aspects of rib width,the depth of grouting and soil strength parameters.Results showed that the horizontal displacement of sheetrib underground continuous retaining wall can be effectively controlled when the grouting soil depth reaches up to 19.5m and the soil body increases its deformation modulus E by 10 times,cohesive force C by 1.5~2 times and internal friction angle φ by 2°~4°.The case studies showed that this reinforcement scheme is reasonable and effective.
引文
[1]张燎军.三峡升船机上闸首结构抗震分析研究[J].水力发电,2000,25(4):19-21.
    [2]梁炯鋆.锚固与注浆技术手册[M].北京:中国电力出版社,1999.
    [3]彭振斌.注浆工程设计计算与施工[M].武汉:中国地质大学,1997.
    [4]范云,卢盛松.挡土墙动力反应及稳定分析[J].河海大学学报,1999,18(4):32-39.
    [5]雷晓燕.岩土工程数值计算[M].北京:中国铁道出版社,1999.
    [6]刘晶波.结构动力学[M].北京:机械工业出版社,2007.
    [7]秦爱芳.上海地区基坑工程中的土体注浆加固研究[J].土木工程学报,2000,33(1):69-72.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心