摘要
为克服某些井试井资料少、难以获取有效产能信息,引入产能刻度因子,基于地质统计学理论,研究了影响小层产能刻度因子的小层有效渗透率、有效厚度的计算方法,建立了使用试井动态资料刻度物探测井静态资料,用刻度后的静态资料进行整个气藏的产能预测。该方法能够充分利用地震、物探和测井等静态信息,结合少量重点井的试井动态解释结果进行产能预测。将该方法应用于M气田的某些井,预测得到的产能接近气井实际产能,满足工程计算的需要。
Due to the limited well test data, it is difficult to obtain effective information about deliverability in some wells. In this paper,the calibration factor of deliverability is introduced and the calculation methods of the influencing factors are studied, to establish a deliverability forecasting method. The geophysical logging static information is first calibrated by the dynamic data of the well test. Then the deliverability of the whole field is forecasted by the calibrated static data. The seismic data, the geophysical logging data at the beginning of exploration and production, and the well test dynamic data of few important wells are made the best use in this method. This method is applied in some wells in the M gas field. The forcasting deliverability results agree well with the actual deliverability. The calculation precision of the new method is high enough to meet the demand of the project design.
引文
[1]李士伦.天然气工程[M].北京:石油工业出版社,2008.Li Shilun.Natural gas engineering[M].Beijing:Petroleum IndustryPress,2008.
    [2]唐洪俊,钟水清,徐永高,等.用不稳定试井确定气井产能方法的评价与研究[J].钻采工艺,2006,29(3):31-32.Tang Hongjun,Zhong Shuiqing,Xu Yonggao,et al.Evaluation andresearch of determining gas well deliverability method by usingnonstabilized well test[J].Drilling&Production Technology,2006,29(3):31-32.
    [3]李治平,赵必荣,张敏渝,等.应用气井压力恢复曲线确定气井产能[J].天然气工业,1998,18(6):63-65.Li Zhiping,Zhao Birong,Zhang Minyu,et al.By use of the pressurebuild-up curve of gas well to determine its productivity[J].Natural GasIndustry,1998,18(6):63-65.
    [4]唐洪俊,赵必荣.用压力恢复试井资料预测气井产能的新方法[J].钻采工艺,1996,19(6):41-43.Tang Hongjun,Zhao Birong.Evaluation and research of determininggas well deliverability method by using the pressure build-up test[J].Drilling&Production Technology,1996,19(6):41-43.
    [5]陈元千.气井垂直管流计算方法的推导与应用[J].断块油气田,2010,17(4):443-447.Chen Yuanqian.Derivation and application of calculating methods ofvertical pipe fiow in gas wells[J].Fault-Block Oil&Gas Field,2010,17(4):443-447.
    [6]吴胜和.储层建模[M].北京:石油工业出版社,1999.Wu Shenghe.Reservoir modeling[M].Beijing:Petroleum Industry Press,1999.
    [7]Jensen C L,Mayson H J.Evluation of permeability determined fromrepeat formation tester measurements made in the Prudhoe Bay field[C]//SPE 60thAnnual Technical Conference,Las Vegas,USA,September 22-25,1985.
    [8]Yildiz Turhan,Langlinais Julius.A reservoir model for wireline formationtesting[C]//SPE Rocky Mountain Regional/Low Permeability ReservoirsSymposium,Denver,USA,March 6-8,1990.
    [9]Semmelbeck M E,Dewan J T,Holditch S A.Invasion-based methodfor estimating permeability from logs[C]//SPE Annual TechnicalConference,Dalas,USA,October 22-25,1995.
    [10]Akram A H,Fitzpatrick A J,Halford F R.A model to predict wirelineformation tester sample contamination[C]//SPE Annual TechnicalConference,New Orleans,Louisiana,USA,September 27-30,1998.