非开挖铺管阻新计算模型及减阻措施
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
在非开挖工程中,计算出当前工艺条件下的铺管阻、选择正确的铺管方法是整个工程成败的关键。通过数学解析方法,重点考虑回拖过程中管道弯曲段弯曲阻的影响,建立了铺管阻新计算模型。实践证明,该模型计算值与实测值仅相差6%,比较符合实际,提出的减阻措施对现场施工也有一定的指导意义。
Calculation for pipelaying resistance in current construction conditions to choose correct pipelaying method is the key for project success in trenchless technology.The paper uses the mathematical analysis method and considers the effect of banding resistance in pulling process to set up the new calculation model.The calculated value of this model is 6 percent difference from measured value,it accords with fact in practice and has less errors and the drag reduction methods are useful for construction.
引文
[1]乌效鸣.导向钻进与非开挖铺管技术[M].武汉:中国地质大学出版社,2004.
    [2]颜纯文,STEIN D.非开挖地下管线施工技术及其应用[M].北京:地震出版社,1999:21-22.
    [3]安金龙.水平定向钻穿越回拖的计算方法及其分析[J].江汉石油科技,2007,17(2):53-58.
    [4]李晓芬,乌效鸣,王海,等.对非开挖钻孔缩径抱管问题的分析探讨[J].探矿工程,2008,35(2):63-65.
    [5]孙训方,方孝淑,关来泰.材料学(上)[M].北京:高等教育出版社,1994:279-280.
    [6]张建民,白景岭.理论学[M].武汉:中国地质大学出版社,1990.