浅埋隧道下穿密集房屋爆破减震技术研究
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
如何正确处理复杂环境下浅埋隧道爆破振害和工程效率之间的矛盾一直是个技术难题。本文依托浅埋下穿重庆市丰都县江池镇标段的长洪岭隧道工程,利用现场监测的方法对不同爆破方案的施工爆破振动进行对比研究,研究表明:采用超前下导坑非爆破开挖+预留光爆层控制爆破开挖技术和上台阶非爆破开挖+下台阶控制爆破技术,成功地将地表爆破振速控制在1.5cm/s以内,在保护建筑物安全的同时,有效保证了该工程的安全快速施工,并为城市环境下隧道爆破掘进工程提供借鉴。
How to deal with a conflict between blasting vibration damage of shallow buried tunnel construction under complex condition and the engineering efficiency has been always a difficult technical problem.Relying on the Changhongling shallow-buried tunnel which under-traverses the Jiangchi Town,using field monitoring method to have comparative study on the blasting vibration under different blasting scheme construction,research shows that: the up-steps of non-blasting excavation + down-steps controlled blasting technique,successfully controls the surface blasting vibration speed within 1.5 cm/s.Then the tunnel can be constructed safely and rapidly,as well as protecting the safety of buildings,this research provides a reference for the blasting excavation engineering in urban area.
引文
[1]李夕兵,凌同华,张义平,爆破震动信号分析理论与技术[M].北京:科学出版社,2009.(Li Xibing,LingTonghua,Zhang Yiping.Analysis of blast vibration sig-nal-theories and methods[M].Beijing:Sciences Press,2009.(in Chinese))
    [2]谢泰极.采用“干扰降震法”通过隧道浅埋地段的控制爆破技术[J].现代隧道技术,2000,(3):28-32.(Xie Taiji.Blasting-control technique“the blasting in-terference of vibration reducing method”adopted in theshallow-embeded section of Yanjin No.1Tunnel[J].Modern Tunneling Techology,2000,(3):28-32.(inChinese))
    [3]周乔勇,尚艳亮,赵玉,等.爆破干扰降震法在隧道爆破施工中的应用[J].铁道建筑,2007,4:52-54.(Zhou Qiaoyong,Shang Yanliang,Zhao Yu,et al.Theblasting interference of vibration reducing method adopt-ed in the tunnel blasting construction[J].Railway En-gineering,2007,(4):52-54.(in Chinese))
    [4]杨千华,张志毅.隧道爆破震动控制技术研究[J].铁道工程学报,2010,(1):82-86.(Yang Qianhua,ZhangZhiyi.Research on the control technology for tunnelblasting vibration[J].Journal of Railway EngineeringSociety,2010,(1):82-86.(in Chinese))
    [5]张艺峰,姚道平,谢志招,等.爆破地震效应主控因素分析及减震措施探讨[J].岩土力学,2010,31(1):304-308.(Zhang Yifeng,Yao Daoping,Xie Zhizhao,et al.Analysis of master control factor of blasting seismic effectand discussion on shock absorption measures[J].Rockand Soil Mechanics,2010,31(1):304-308.(in Chi-nese))
    [6]赵福兴.控制爆破工程学[M].西安:西安交通大学出版社,1988.(Zhao Fuxing.Control blasting engineer-ing[M].Xi’an:Xi’an Jiaotong University Press,1988.(in Chinese))
    [7]李冀祺,马素贞.爆炸力学[A].北京:科学出版社,1992.(Li Yiqi,Ma Suzhen.Explosion mechanics[A].Beijing:Sciences Press,1992.(in Chinese))
    [8]易长平,陈明,卢文波,等,减震沟减震的数值模拟[J].武汉大学学报(工学报),2005,38(1):49-52.(Yi Changping,Chen Ming,Lu Wenbo,et al.Numeri-cal simulation for damping effect of damping ditch[J].Journal of Wuhan University of Hydraulic and ElectricEngineering,2005,38(1):49-52.(in Chinese))
    [9]爆破安全规程(GB67222003)[S].北京:中国标准出版社,2003.(China State Bureau of Standards.Safetyregulations for blasting(GB6722 2003)[S].Beijing:China Standards Press,2003.(in Chinese))
    [10]张世雄,胡建华,阳生权,等.地下工程爆破振动监测与分析[J].爆破,2001,18(2):49-52.(Zhang Shix-iong,Hu Jianhua,Yang Shengquan,et al.Monitoringand analysis of blast vibration in underground engineer-ing[J].Blasting,2001,18(2):49-52.(in Chinese))
    [11]杨朝阳.城市浅埋隧道爆破地震波的降振技术[J].福建建设科技,2009,(5):70-72.(Yang Chaoyang.Vibration reducing technique for urban shallow-buriedtunnel blasting[J].Fujian Construction Science&Te-chology,2009,(5):70-72.(in Chinese))
    [12]王焱,欧阳天烽,谭绪凯.特大断面隧道爆破开挖方法对比分析研究[J].西南交通科技,2010,(4):50-57.(Wang Yan,Ouyang Tianfeng,Tan Xukai.Thecomparison of blasting and excavation method on largecross-section tunnel[J].Western China CommunicationScience&Technology,2010,(4):50-57.(in Chi-nese))
    [13]张胜龙.复杂环境下地铁明挖深基坑的爆破施工[J].城市轨道交通研究,2010,(2):65-68.(ZhangShenglong.Deep pit blasting in metro construction un-der complex environment[J].Urban Mass Transit,2010,(2):65-68.(in Chinese))
    [14]U.兰格福斯,B.基尔斯特略著.岩石爆破现代技术[M].北京:冶金工业出版社,1983.(U.Langefors B.Kihlstrom.The modern technique of rock blasting[M].Beijing:Metallurgical Industry Press,1983.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心