空孔对爆破地震波减震作用的数值模拟分析
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
南京红山南路新开挖隧道群上跨既有地铁1号线,最短垂直距离仅为4.16 m。在爆破施工过程中,为确保运行地铁的安全,采用了在隧道开挖层和地铁隧道中间打空孔的减震技术。结合红山南路隧道开挖实际工程,利用AUTODYN软件对工程中有减震空孔情况下的爆破进行数值模拟计算,分析了减震空孔排数、空孔与爆源距离等空孔布置参数对爆破地震波的衰减影响。对空孔的布置参数进行优化,提出了在距离爆源1 m处打2排交错空孔的减震方案,实际工程中震动速率减小率达49.8%,减震效果明显。
The vertical distance from the excavation face of new tunnels at Hongshan South Road in Nanjing to the existent NO.1 subway tunnel is only 4.16 m.To keep the subway operation safe,the seismic control method by drilling empty holes between the excavation face and the existent tunnel was applied in the blasting engineering.Based on actual excavation engineering in Hongshan South Road Tunnel,the software AUTODYN was used to simulate the blasting process.The effect of damping holes range number and distances from damping holes to blast source on attenuation law during the blasting seismic wave propagation in the rock was analyzed.By optimizing the setting parameter of the damping holes,a scheme of drilling double range staggered holes within 1 meter near the blast source was proposed.The peak particle vibration velocity was reduced 49.8%.
引文
[1]梁开水,陈天珠,易长平.减震沟减震效果的数值模拟研究[J].爆破,2006,23(3):18-21.[1]LIANG K SH,CHENG T ZH,YI CH P.Numerical simu-lation for vibration-isolating effect of vibration-isolatingslot[J].Blasting,2006,23(3):18-21.(in Chinese)
    [2]谢先启.精细爆破[M].武汉:华中科技大学出版社,2010:128-131.
    [3]三三零工程局.葛洲工程施工技术汇集(一)[M].宜昌:三三零工程局,1978.
    [4]楼晓明,赖红源,唐小军.紫金山金铜矿靠帮高陡边坡爆破减震研究[J].爆破,2011,28(2):56-59.[4]LOU X M,LAI H Y,TANG X J.Study on blasting vibra-tion absorbing of high rock end-slope in Zijinshan Gold-copper Mine[J].Blasting,2011,28(2):56-59.(in Chi-nese)
    [5]邹绍明.矿山控制爆破技术在城市地下大断面轻轨施工中的应用[J].爆破,2011,28(3):52-55.[5]ZOU SH M.Mine controlled blasting techniques appliedin light railway constructions of large cross-section underthe city[J].Blasting,2011,28(3):52-55.(in Chinese)
    [6]周传波,谷任国,罗学东.坚硬岩石一次爆破成井掏槽方式的数值模拟研究[J].岩石力学与工程学报,2005,24(13):2298-2303.[6]ZHOU C B,GU R G,LUO X D.Numerical simulation oncutting mode of shaft excavation by one-step deep-holeblasting in hard rock[J].Chinese Journal of Rock Me-chanics and Engineering,2005,24(13):2298-2303.(inChinese)
    [7]Century Dynamics Inc.AUTODYN users manual[M].Centu-ry Dynamics Inc,1997.
    [8]叶序双.爆炸作用理论基础[M].南京:工程兵工程学院,1996:142-143.
    [9]徐平,夏唐代,周新民.单排空心管桩屏障对平面SV波的隔离效果研究[J].岩土工程学报,2007(1):131-136.[9]XU P,XIA T D,ZHOU X M.Study on effect of barrier ofa row of hollow pipe piles on isolation of incident planeSV waves[J].Chinese Journal of Geotechnical Engineer-ing,2007(1):131-136.(in Chinese)