紫坪铺水利枢纽垫层管取代伸缩节的地震响应分析
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
结合紫坪铺水利枢纽工程的实际,采用三维有限元方法对该工程发电引水系统取消伸缩节后的抗震性能进行了研究。计算结果表明,主厂房上游永久分缝处以一段垫层管代替常规伸缩节以后,压力管道在地震荷载和内水压力等荷载组合作用下,结构的动力响应可以满足使用要求,从而达到取消伸缩节、节省工程投资的目的。
In accordance with the practice of Zipingpu hydraulic engineering project, a study on the earthquake resistance after cancellation of expansion joints in the conduit system ahead of powerhouse has been carried out by means of 3-D FEM. Results of calculation show that it is absolutely feasible to replace the expansion joint ahead of the powerhouse by a steel pipe with cushion layer outside, considering the common effect of earthquake and inside water pressure. As a result, the engineering investment can be saved because of the cancellation of expansion joints.
引文
[1]申艳,伍鹤皋,蒋逵超,等.紫坪铺水利枢纽引水系统取消厂前伸缩节研究[ J].中国农村水利水电,2004(6):72-74
    [2]李爱群,高振世.工程结构抗震与防灾[M].南京:东南大学出版社,2003.
    [3]国家电力公司西北勘测设计研究院,国家电力公司昆明勘测设计研究院.水电站压力钢管设计规范DL/T5141-2001[S].北京:中国电力出版社,2002.
    [4]董毓新,李彦硕.水电站建筑物结构分析[M].大连:大连理工大学出版社,1995.
    [5]傅金筑,张淑婵,李家峡水电站钢管取消伸缩节论证[J].水电站压力管道情报网网讯,1994(2):20-28

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心