浅埋煤层群大采高采场初次来压顶板结构及支架载荷研究
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Research on roof structure and support resistance during first periodic weighting in shallow group coal seams
  • 作者:黄庆享 ; 黄克军 ; 赵萌烨
  • 英文作者:HUANG Qingxiang;HUANG Kejun;ZHAO Mengye;School of Energy Engineering,Xi'an University of Science and Technology;Shaanxi Coal and Chemical Technology Institute Company Limited;
  • 关键词:近距离煤层群 ; 初次来压 ; 顶板结构 ; 动静载荷 ; 支架阻力计算
  • 英文关键词:close coal seam group;;first periodic weighting;;roof structure;;static and dynamic load;;support resistance
  • 中文刊名:KSYL
  • 英文刊名:Journal of Mining & Safety Engineering
  • 机构:西安科技大学能源学院;陕西煤业化工技术研究院有限责任公司;
  • 出版日期:2018-09-15
  • 出版单位:采矿与安全工程学报
  • 年:2018
  • 期:v.35;No.140
  • 基金:国家自然科学基金项目(51674190,51174278);; 陕西省科技统筹创新工程计划项目(2011KTZB01-02)
  • 语种:中文;
  • 页:KSYL201805009
  • 页数:5
  • CN:05
  • ISSN:32-1760/TD
  • 分类号:68-72
摘要
以陕北榆神矿区浅埋近距离煤层群下行开采为背景,通过物理模拟研究了下煤层工作面初次来压的顶板结构特征。近距离煤层下煤层开采时,间隔岩层顶板一般具有单一关键层,顶板初次破断形成"非对称三铰拱结构",结构上的载荷层为上煤层采空区垮落顶板。上煤层垮落顶板结构在下煤层采动后活化,与下煤层三铰拱结构共同形成"非对称三铰拱梁与拱壳载荷结构"。通过建立浅埋煤层群下煤层关键层固支梁力学模型,修正了基本顶极限垮距计算公式,确定了下煤层顶板结构块的参数。建立了煤层群下煤层开采初次来压的支架载荷计算模型,揭示了工作面顶板动压机理。基于动静载荷作用,提出了初次来压的合理支架工作阻力确定方法,为浅埋近距离煤层群开采的顶板初次来压控制提供了理论依据。
        Based on the background of shallow and close coal seam group downward mining in Yulin-Shenmu mining area in northern Shaanxi, through the physical simulation of roof structure characteristics during the first roof periodic weighting in lower coal seams. In the close coal seams mining,the interval layer roof generally has a single key stratum. The roof's first breaking forms an "asymmetric three hinged arch structure" and the load layer on the structure is the caving roof of the upper coal seam. The caving roof structure of upper coal seam is activated after lower coal seam mining and combines with the three hinge arch structure of the lower seam together to form the "asymmetric three hinged arch with arch shell load structure". By establishing the clamped beam mechanical model of the key stratum of lower coal seam roof in the shallow coal seam group mining, the calculation formula of the ultimate collapse distance of the interval layer roof is modified and the parameters of the roof structure blocks of the lower coal seam are determined. The support static load calculation model of the first periodic weighting in lower seam mining is established. Thus, the mechanism of the roof dynamic pressure of the mining face is revealed. Based on the static and dynamic load, the method of determining the reasonable support resistance is proposed, which provides a theoretical basis for the roof first periodic weighting control in shallow and close coal seams mining.
引文
[1]黄庆享.浅埋煤层长壁开采顶板结构及岩层控制研究[M].徐州:中国矿业大学出版社,2000:89-91.
    [2]黄庆享.浅埋煤层的矿压特征与浅埋煤层定义[J].岩石力学与工程学报,2002,21(8):1174-1177.HUANG Qingxiang.Ground pressure behavior and definition of shallow seams[J].Chinese Journal of Rock Mechanics and Engineering,2002,21(8):1174-1177.
    [3]黄庆享,钱鸣高,石平五.浅埋煤层采场基本顶周期来压的结构分析[J].煤炭学报,1999,24(6):581-585.HUANG Qingxiang,QIAN Minggao,SHI Pingwu.Structural analysis of main roof stability during periodic weighting in long wall face[J].Journal of China Coal Society,1999,24(6):581-585.
    [4]黄庆享,刘文岗,田银素.近浅埋煤层大采高矿压显现规律实测研究[J].矿山压力与顶板管理,2003,20(3):58-59.HUANG Qingxiang,LIU Wengang,TIAN Yinsu.Observation on the law of strata behavior in shallow seam and high mining height face[J].Ground Pressure and Strata Control,2003,20(3):58-59.
    [5]缪协兴.采场基本顶初次来压时的稳定性分析[J].中国矿业大学学报,1989,18(3):88-92.MIAO Xiexing.Stability analysis of the main roof during first weighting in longwall face[J].Journal of China University of Mining&Technology,1989,18(3):88-92.
    [6]HUANG Qingxiang.Analysis of main roof breaking form and its mechanism during first weighting in longwall face[J].Journal of Coal Science&Engineering(China),2001,7(1):9-12.
    [7]黄庆享,祈万涛,杨春林.采场基本顶初次破断机理与破断形态分析[J].西安矿业学院学报,1999,19(3):193-197.HUANG Qingxiang,QI Wantao,YANG Chunlin.Analysis of the broken block during the first weighting in shallow working face[J].Journal of Xi’an Mining Institute,1999,19(3):193-197.
    [8]黄庆享.采场基本顶初次来压的结构分析[J].岩石力学与工程学报,1998,17(5):521-526.HUANG Qingxiang.Structural analysis of main roof stability during first weighting in long wall face[J].Journal Chinese Journal of Rock Mechanics and Engineering,1998,17(5):521-526.
    [9]黄庆享.浅埋采场初次来压顶板砂土层载荷传递研究[J].岩土力学,2005,26(6):881-883.HUANG Qingxiang.Study on load transmitting factor of thick sandy soil on key roof stratum during first weighting in shallow seam[J].Rock and Soil Mechanics,2005,26(6):881-883.
    [10]王家臣,王兆会.浅埋薄基岩高强度开采工作面初次来压基本顶结构稳定性研究[J].采矿与安全工程学报,2015,32(2):175-181.WANG Jiachen,WANG Zhaohui.Stability of main roof structure during the first weighting in shallow high-intensity mining face with thin bedrock[J].Journal of Mining&Safety Engineering.2015,32(2):175-181.