基于高拱坝坝体生长特征的缆机调度仿真研究
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Study on Cable Machine Scheduling Simulation Based on Growth Characteristics of High Arch Dam
  • 作者:杨忠加 ; 周宜红 ; 胡超 ; 贺俊
  • 英文作者:YANG Zhong-jia;ZHOU Yi-hong;HU Chao;HE Jun;College of Hydraulic and Environmental Engineering,China Three Gorges University;Hubei Key Laboratory of Construction and Management in Hydropower Engineering,China Three Gorges University;
  • 关键词:高拱坝 ; 坝体生长特征 ; 缆机调度 ; 坝体生长步—缆机供需关系
  • 英文关键词:high arch dam;;growth characteristics of the dam body;;cable machine scheduling;;supply and demand relation of the growth step of dam body
  • 中文刊名:SDNY
  • 英文刊名:Water Resources and Power
  • 机构:三峡大学水利与环境学院;三峡大学湖北省水利水电工程施工与管理重点实验室;
  • 出版日期:2018-05-22
  • 出版单位:水电能源科学
  • 年:2018
  • 期:v.36;No.213
  • 基金:国家自然科学基金项目(51479103);; 水利水电工程施工与管理湖北省重点实验室(三峡大学)开放基金项目(2016KSD09)
  • 语种:中文;
  • 页:SDNY201805039
  • 页数:5
  • CN:05
  • ISSN:42-1231/TK
  • 分类号:164-168
摘要
高拱坝通常施工场地狭窄,且混凝土浇筑与其他作业相互交叉干扰,对缆机调度影响较大。为了研究高拱坝坝体生长特征与缆机调配之间的关系,以坝体生长的过程为主线,分析了高拱坝坝体生长的时空特征,从正向考虑了不同坝体生长特征的缆机调配方式,反向调整了满足缆机浇筑的坝体生长步,并从坝体生长—缆机调配系统互为因果的特点出发对坝体生长方案进行优化。实例仿真结果表明,优化浇筑方案后的混凝土入仓强度更均衡,缆机利用率得到提升,对缆机实时调配和坝体生长均有积极意义。
        The high arch dam usually has a narrow construction site,and the concrete pouring interacts with other operations to interfere with each other,which has a great influence on the cable machine scheduling.In order to study the relationship between the growth characteristics of high arch dam and cable deployment,this paper takes the process of dam growth as the main line,and analyzes the spatio-temporal characteristics of high arch dam growth.The cable deployment method considering the growth characteristics of different dams was adjusted from the forward direction,and the dam growth step was adjusted in the reverse direction to meet the cable casting.Considering the mutually causal characteristics of the growth of dam body-the deployment system of cable machine,the dam growth plan was optimized.The engineering examples show that the optimized pouring scheme has positive significance for the real-time deployment of cable machines and dam growth.The pouring strength of concrete is more equilibrium and the utilization ratio of cable machine is promoted.
引文
[1]巨亚东,郭万里.多台缆机联合浇筑工艺在小湾水电站大坝混凝土浇筑中的应用[J].西北水电,2010(4):59-63.
    [2]周厚贵,戴志清,张开广,等.混凝土坝浇筑机械联合施工的模拟优化及其应用[J].三峡大学学报:自然科学版,2014,36(2):6-10.
    [3]周宜红,定兰,赵春菊.碾压混凝土坝施工浇筑系统仿真模型研究[J].水电能源科学,2006,24(1):50-51,89.
    [4]夏大勇,练柳君,张辉.亭子口缆机运行效率提高的工作研究[J].水力发电,2013,39(6):86-88.
    [5]谢洪林,郭建文,刘金山,等.小湾水电站拱坝施工中缆机的运行管理与探索[J].水力发电,2009,35(9):94-97.

© 2004-2018 中国地质图书馆版权所有 京ICP备05064691号 京公网安备11010802017129号

地址:北京市海淀区学院路29号 邮编:100083

电话:办公室:(+86 10)66554848;文献借阅、咨询服务、科技查新:66554700