摘要
基于我国垃圾焚烧发电厂运行特点及蒸汽旁路系统的作用,介绍了垃圾焚烧发电厂大旁路蒸汽冷凝系统的主要工艺流程,并以某实际垃圾焚烧处理工程为例,确了定大旁路蒸汽冷凝系统的主要设备参数。
Based on operation characteristics of waste incineration power plant and role of steam bypass system in China, the main process of large bypass steam and condensate system in waste incineration power plant was introduced, and taking a practical project of waste incineration treatment as an example,the main equipment parameters of large bypass steam and condensation system were determined.
引文
[1]王中民.城市生活垃圾处理与处置[M].北京:中国建筑工业出版社,1991.
[2]张益,赵由才.生活垃圾焚烧技术[M].北京:化学工业出版社环境科学与工程出版中心,2000.
[3] CJJ90—2009.生活垃圾焚烧处理工程技术规范[S].
[4]白良成.生活垃圾焚烧处理工程技术[M].北京:中国建筑工业出版社,2009.
[5]王志伟.汽轮机运行[M].北京:中国电力出版社,2007.
[6]洪向道.中小型热电联产工程设计手册[M].北京:中国电力出版社,2006.
[7] GB 50049—2011.小型火力发电厂设计规范[S].